BAE422 Estimating ( 2 pt)—YTU Reference
www.iqytechnicalcollege.com/BAE422Estimating.pptx
Study
CE115 Estimation & Specification
Instruction Audio Files
http://www.filefactory.com/file/3408tnqnyrvn/CE115_Instruction%20Audio%20Files%20for%20Part%201.zip
http://www.filefactory.com/file/377jpgzqggi3/CE115_Instruction%20Audio%20Files%20for%20Part%202.zip
Reference Textbooks & Exercises (Based on UK Standard)
What to read
CE 115 Part
1---- Civil Engg Part 9—Page 40 to 100
together
with audio support files and do the following exercises.
(R782)
http://www.filefactory.com/file/4w0onks81o5h/n/Civil_Engg_Part_9_pdf
Page |
Contents |
Unit Code |
38-100 |
Builder Estimating |
Building Construction |
Civil Engg
Part 9
Page 40 to
41
Q1. What are
the contents to be included in contract document?
Page 44
Q2. What are
to be included in estimate?
Page 45
& 49+ 50
Q3.What are to be included in labour’s cost?
Page 62
Q4. Provide
the summary of bills of quantity.
Page 64
Q5. Explain
the followings
(a) Base time (b) Standard rating.
Page 65
Q6. Provide
the equation to calculate standard time of bricklayer.
Page 68.
Q7. Explain
the followings
(a) c & f (b) COD (c) FOB
Page 69
Q8.Describe the cost of operating builder’s lorry.
Page 72+73
Q9.What are the costs of mechanical plant?
Page 79
Q10. What
are the rates of cost for excavation and earth work?
Page 86
Q11. What
are the rates of cost for brick work & block work?
Page 92.
Q12. What
are the rates of cost for bubble walling and masonry?
Page 98.
Q13. What
are the rates of cost for carpentry?
Study CE115
Estimation & Specification
CE 115 Part
2---- Civil Engg Part 8—Page 1 to 33
(R781)
http://www.filefactory.com/file/5nmrpczy39jh/n/Civil_Engg_Part_8_pdf
Page |
Contents |
Unit Code |
1-100 |
Specification, Estimating |
Civil Engineering |
together
with audio support files and do the following exercises.
Password--- iqytechnicalcollege
Civil Engg
Part 8
Slide 2
Q1.What are the rates of cost for joinery?
Slide 8
Q2. What are
the rates of cost for plumbing and engineering installations?
Slide 12
Q3. What are
the rates of cost for electrical installations?
Slide 14
Q4. What are
the rates of cost for plaster work, ceiling and floor finishes?
Slide 19
Q5. What are
the rates of cost for glazing?
Slide 21
Q6. What are
the rates of cost for painting and decorating?
Slide 23
Q7. What are
the rates of cost for drainage?
Slide 25.
Q8.Explain pro-rata rates?
Slide 27 to 33.
Q9.Explain incentive scheme.